Thursday, May 10, 2007

Which point we are in the time line

Until this time, we are now keeping in touch with the Gantt Chart regarding the project's deadline that the client set to us.

We have finished 90% of the flash, including the main flash, and sub flashes.

We have received lots of valuable feedbacks from the classmates today. They got some problems with navigating around the site; it took them few seconds to get what they wanted; the audio also needed to be adjusted by the users through a slide bar.

Here are few things that need to be done in the next couple of days:
  1. Add data [information] into the flash, including dance history, contact information, credit.
  2. Fix the navigation.
  3. Sound control panel.

Wednesday, April 25, 2007

Shoot Video again

Friday (27th April): 10:00am - 12:00pm
  • Quy Lam + Tam
  • NOTE: for the first 15 mins, test for the light, import video into computer to see the result.

Tuesday (1st May): 2:00pm - 4:00pm

  • Urko + Ha

Problems for today post-production

1. Transparent bacground can not be applied to DVCPRO HD(720p) 16:9
Solution:
  • Convert DVCPRO 720p into PAL
  • OR record in PAL (720 x 576)

2. The video is so dark
Solution:

  • Set up more lighting.

Sunday, April 22, 2007

We got some problems with HD video

Because of the want to have a really good video quality, we have decided to shoot the video at 1080i resolution. Then, we have over 15 GB for 15 mins of video and that's big!
The machine took a long time to post-process.
--> It's not feasible!

So, we decided to reduce the resolution for the next shooting to 720x576.

Saturday, April 14, 2007

Latest News for Week 7

The project is going to its hard phase;
We have decided each member's role for the next week:
  • Lam: makes graphic pieces used for flash, including vectors and bitmaps.
  • Cuong: responsible for handle the recompose the music
  • Trung: works on the action scripts, and layout the flash structure.

Thursday, April 5, 2007

A successful video testing

Together with Justin, our tutor, we have shooted some pieces of video by his High-Definition Camera.
The result was so so so good, we were totally satisfied with it! ^_^

Thanks Justin!

Friday, March 30, 2007

Schedule for week 6 and 7

Week 6:

Tuesday (3th Apr) & Saturday (7th Apr)
  • Studio 1 booking
    9h-11h --> Lam
    11h-1h --> Cuong
    1h-3h --> Trung
    3h-5h --> Lam
  • Lighting Room (studio 4)
    9h-11h --> Cuong
    11h-1h --> Trung
    1h-3h --> Lam
    3h-5h --> Cuong

Friday (6th Apr 2007)

  • Studio 1 booking
    2h-4h --> Lam
    4h-6h --> Cuong
    6h-8h --> Trung
  • Lighting Room (studio 4)
    2h-4h --> Cuong
    4h-6h --> Trung

Week7: the same as week 6

NOTE: need to work with Justin on Tuesday (week 6) --> let's check if he is availble!