Thursday, May 10, 2007

Which point we are in the time line

Until this time, we are now keeping in touch with the Gantt Chart regarding the project's deadline that the client set to us.

We have finished 90% of the flash, including the main flash, and sub flashes.

We have received lots of valuable feedbacks from the classmates today. They got some problems with navigating around the site; it took them few seconds to get what they wanted; the audio also needed to be adjusted by the users through a slide bar.

Here are few things that need to be done in the next couple of days:
  1. Add data [information] into the flash, including dance history, contact information, credit.
  2. Fix the navigation.
  3. Sound control panel.